Thursday, February 21, 2013

Shiny

 We were on a slight hold waiting for our special order electrical panel. It came in this morning and we did a pre-breakfast run to pick it up. Kevin built a new wall in the basement for it. He also rewired the main power cable, the furnace, and the one outlet to the side. That would equal the total power in the house. The new panel is definitely larger than the old and will be open for expansion sometime in the future. By moving it to the basement we also will be better prepped to rewire.
New Panel
Old Panel
While Kevin was working on the wall and electrical, I was upstairs taking down ceiling tiles and the kitchen drywall.

After the furnace was back up and running we went back to the subfloor and now have half a floor to walk on!

 With the new floor I'll be able to pull down more ceiling tiles! We are down to only one shelf along the back wall. I got rid of the top one and the box shelf set which opened the corner up for demo.
View from the front door


1 comment: